ca roles and responsibilities - 9 - CONTRACT INSTRUCTIONS / VARIATONS
|
In the majority of cases, contract instructions will be generated by either the design team or the contractor. Circumstances in which this may occur include:
The CA will need to be aware of the cost implications of issuing instructions (which may be additions, neutral or deductions). The calculation of those costs should be in accordance with the rules set out in the building contract. Where such instructions give rise to additional costs outside the building contract provisions, or the CA’s appointment, then the employer’s approval for the expenditure will need to be sought before the instruction is given. The CA should consider the impact instructions will have on the programme and sequence of works, as well as the contract completion date. The CA should make the employer aware of the implications. |