ca roles and responsibilities - 4 - MEETINGS
|
Meetings attended by the CA may be formal or informal and for whatever the purpose, should be recorded for the file, particularly where actions need to follow.
Informal meetings on site, may be with operatives, contracts managers, specialist suppliers, other professionals or indeed the employer. Some projects will have formal progress meetings which the CA will attend or may even chair. Such meetings should be minuted and issued very soon afterwards to clearly record the decisions taken and actions required. Normally it should be possible to agree a programme of meetings at the commencement of a building contract, and typically formal meetings will cover such matters as:
It is normal to have an initial meeting soon after the order for the works has been placed by the employer to ‘set the scene’; often this meeting is termed the ‘pre-contract’ meeting although strictly speaking it is a ‘pre-commencement’ |